May 2018 to November 2018
May 2018 to November 2018
$1,339,829
Longmont United Hospital (LUH)
TreanorHL (formerly H+L Architecture)
MRI Suite renovation to replace equipment and make modifications to the surrounding support spaces. The project included replacing a magnet which required installation through an existing skylight. Critical care systems (medical gases, electrical systems, HVAC, and plumbing) were kept operational at all times during construction. The work was conducted adjacent to a fully-operational imaging department at the hospital. A temporary mobile MRI unit was required to keep MRI imaging services available for the hospital.